CARE crack injection works at 14 Collins Road St Ives

Project Case Study, Crack Injection

Crack Injection & Basement Repair at 14 Collins Road, St Ives.

CARE was engaged by Trescon Constructions to assess and treat cracking to in-situ concrete retaining walls in a newly constructed residential basement.

47 LMCrack length treated
3Day programme
52 LVSikadur system
Full-depthSikadur 52 LV
Client / BuilderTrescon Constructions
Location14 Collins Rd, St Ives NSW
ScopeBasement Crack Injection
Injection SystemSikadur 52 LV
Surface SealSikadur 31 Epoxy Paste
Duration3-Day Programme, April 2026

01, Background

The Challenge

An extensive network of cracks had developed across the basement retaining walls of a newly constructed residential development, with active water ingress evident across multiple panels.

CARE was engaged by Trescon Constructions following an on-site inspection to assess and treat cracking to the in-situ concrete retaining walls of the basement structure. The cracks ranged from fine shrinkage cracks to wider diagonal and structural cracks, with water staining and seepage visible across several areas.

The basement environment presented multiple challenges: restricted access in some bays, services and pipework running across the face of the walls, cracks extending to the soffit-wall junction, and a high standard of finish required by the principal contractor.

03, Methodology

How We Did It

1

Full crack survey conducted prior to mobilisation. All affected areas confirmed with the site supervisor. SWMS reviewed and approved by Trescon before works commenced.

2

Low-pressure injection packers drilled and installed at 150-200 mm centres along each identified crack, including areas at high level and near the soffit.

3

Crack faces sealed between packers with Sikadur 31 two-part epoxy paste, creating a pressure-tight surface seal to allow effective pressurisation during injection.

4

Sikadur 52 LV injected using a manual two-component cartridge gun, working sequentially from the lowest packer upward. Resin return from adjacent packers confirmed full-depth penetration before moving on.

5

Packers removed, surface seal ground back on cure. Daily dockets signed by the site team. Full ITP with photo record submitted to Trescon on demobilisation.

02, Scope of Works

What We Did

05, Outcome

Result

All 47 linear metres of crack injection works were completed within the planned three-day programme and within the agreed scope. The Sikadur 52 LV epoxy penetrated the full depth of the wall sections, providing structural consolidation of the crack planes and sealing active seepage paths where present.

An Inspection and Test Plan (ITP) with a full photographic record organised by day was submitted to Trescon on completion. The project demonstrates CARE’s capability in managing technically complex crack injection programmes within occupied and serviced basement environments.